Wick Farm Solar Project near Melksham

Work started in mid-December 2024 to erect 13,000m of fencing around the farm site.  So far, we’re up to about 10,000m.

We are using our Evo 3 post driver/creosote timber posts with Solonet deer wire unrolled /tensioner with Tornado 450m rolls of deer netting.  The timber we are using is supplied and treated in the UK and we are using UK-manufactured wire netting.

These 450m rolls have been specially ordered for this project instead of the standard 100m, to reduce the amount of joining.  

The site consists of 16 separate compartments of solar panels. We have installed gates along with the fences and ED & W Bodman have installed all tracks.

It was nice to see the sun one-day last week!

Here Tristan and Toby are flying along with the fencing.

Solar Farm Project fencing